The Cape Charles Town Council has amended the BBA contract to scope the environmental assessment work needed at the potential construction site. Council added $6988 to the contract- $5,040 for an environmental assessment of the potential construction site, and $1,948 to add the library function to Phase 1.
Cape Charles has been working with HBA and their proposed sub-consultant, MSA, to scope the environmental assessment work needed at the potential construction site.
A Phase 1 ESA will not be necessary. Enough data about prior use of that land and the surrounding area is already available. MSA recommends soil and water sampling to determine if there is any significant contamination from the adjacent former dump site.
The VDOT survey for construction of Cassatt Parkway contains a non-tidal wetlands delineation for the low area along the right-of-way, so only a wetlands assessment for the remaining portion of the site is really needed.
The total fee for this environmental assessment would be $5,040. This would bring the contract value to $46,549, or $1,549 over the $45,000 authorized.
Additionally, HBA has a proposed a fee of $1,948 to add the library function to the Phase 1 scope of work. According to the staff report, there is enough funding budgeted for the project to handle the additional work.

Of course it's his business how much water the concrete plant uses. This is still America, afterall. And where are…
It is none of your damn business how much water the concrete plant uses. You seem like a busy body.…
According to the Cape Charles Mirror (10/11/26), in the article on “Cape Charles Advances Municipal Building, Harbor Boardwalk and Infrastructure…
Thank you very much for your prompt edit 😊
You’ve posted a photo of Eyre Hall. This can be very misleading. Please correct. Editor's Note: Thanks for the catch!…