Last spring, the inshore breakwater near the harbor was was damaged when a vessel strafed the northern end. A portion of the horizontal timber waler was broken, many of the piling bolts were sheared, one section of sheet piling was also damaged.
The firm of Langley & McDonald has noted that the breakwater is in critical condition and in danger of structurally failing during a severe storm event. Langley has provided a scope of work for the needed repairs.
Marine Contracting Corporation submitted a bid in the amount of $121,380. Marine Contracting Corporation was the company that built the in-shore breakwater and is familiar with the design
The Town received funding from the American Rescue Plan Act (ARPA) grant ($528,615), and funding for the breakwater repairs will most likely be derived from this grant.
Town Council will vote on this measure at the next Regular Meeting this Thursday.

You would have to be a complete idiot to walk around with a tie around your neck in the first…
Kinda' on a different note: Also curious about how Eastville will be compensated or supported if catches drop.
After reading this story I suppose that there are some advantages to going full tilt Cold Turkey...
The Eastern Shore is very easy to see on that ugly necktie.
Good overview and clear summary. Do you know if the commission provided regional breakdowns of the quota cuts and how…