Last spring, the inshore breakwater near the harbor was was damaged when a vessel strafed the northern end. A portion of the horizontal timber waler was broken, many of the piling bolts were sheared, one section of sheet piling was also damaged.
The firm of Langley & McDonald has noted that the breakwater is in critical condition and in danger of structurally failing during a severe storm event. Langley has provided a scope of work for the needed repairs.
Marine Contracting Corporation submitted a bid in the amount of $121,380. Marine Contracting Corporation was the company that built the in-shore breakwater and is familiar with the design
The Town received funding from the American Rescue Plan Act (ARPA) grant ($528,615), and funding for the breakwater repairs will most likely be derived from this grant.
Town Council will vote on this measure at the next Regular Meeting this Thursday.

Hank - why else do all the been heres hate all the come heres? The come heres made the been…
Laughing King, why do you keep repeating the same thing over and over about your father getting rich from selling…
I’ve never seen a group of people so butthurt. If you don’t like the come here’s, stop selling your land…
If so, how on earth did the Eastern Shore feed, educate, and house it's citizens before now? The only difference…
This is great news for our town and county. We cannot expect to have good restaurants, schools, etc., if we…