Wastewater Notes
The Wastewater plant treated an average of 170,683 gallons a day. The highest usage was on May 17, using 202,625 gallons. Utility Staff continued daily water quality testing and analysis, submitted Monthly reports completed for VDH.
Water Plant
Staff Performed Daily water quality testing and analysis, and submitted Monthly reports for VDH.
Water Usage:
- WTP operated for 82 hours with the average daily operation of 11.7 hours
- 1,141,904 gallons produced with approx. 145,000 gallons used for processes
- 163,129 average daily production with peak of 205,594 on 5/7/23
(5/12-5/18) - WTP operated for 87.5 hours with the average daily operation of 12.5 hours
- 1,234,318 gallons produced with approx. 145,000 gallons used for processes
- 176,331 average daily production with peak of 197,017 on 5/12/23

Someone please explain the need to turn the bike trail south, across Route 13 (the Shore’s interstate), and then turn…
My biggest issue with it currently is, it gives the most likely answer not always the actual answer. AI gives…
Congratulations Cheryl....you have raised the ire of Nokia Marshall....two time failed candidate for town council. I have observed her nasty,…
This project reminds me of the H-3 Highway Project in Hawaii and the $640°° Pentagon toilet seats.....
Thank Goddess they didn't vote you in! p.s. you don't live with me, you're not my friend so stop claiming…