Update: After the joint meeting, Cape Charles PSA rep Bob Panek forwarded his take on events to Town Manager Manuel and Mayor George Proto:
George & Brent,
The PSA Board met with the County BoS last evening to brief the status of the Southern Node Commercial, Phase 1 wastewater project. The briefing covered:
1. Status of engineering.
2. Project cost estimate.
3. Engineering & construction timeline.
4. Draft treatment agreement with Cape Charles, including outstanding issues: surcharge, connection charge, zoning overlay district for SR 184/US 13.
5. Special Tax District and tax ratios.
6. County advance for operations costs and first bond payment.
7. County obligation for PSA bonds.
8. PSA operations and maintenance costs.
After the briefing, the BoS voted to suspend further work on the project until the issues surrounding the agreement with Cape Charles can be resolved.
The day after the recent Work Session, I advised the County Administrator relative to the zoning overlay district being a precursor to moving forward on an agreement. I recommend that the Town formally transmit this position to the County Administrator so that a Council/BoS meeting can be scheduled.
Bob
At the June 22nd joint meeting with Northampton Board of Supervisors and the Public Service Authority (PSA), the Boardย sent a clear message that they have more importantย priorities thanย the PSA pipeline project, and that they were not going to give in to what Katie Nunez, and several members of the audience called blackmail by the Town of Cape Charles. The board voted to put the entire PSA project on hold for the foreseeable future. ย โI have a very big problem with the Cape Charles contract. The cost, the profit (for Cape Charles), and the way they want to hold zoning over our heads. Iโve got a big problem with that, โsaid Larry LeMond. โWe have EMS issues, we have school issues,โ added Supervisor Hogg. โWe have important issues that need to be addressed first. The PSA is going to have to take a back seat.โ
PSA chairman John Reiter was on hand to provide an in-depth overview of just where the PSA project stands. According to Reiter, the preliminary engineering by Hurtt & Profitt, which makes up 40% of the overall project, has been completed. Responding to a question by Chairman Hubbard, Reiter responded that the county has spent $78,000 on the project to date.
A major issue still outstanding is the negotiations with Cape Charles. There is a draft agreement, but there are also two outstanding issues. The first is the cost per gallon. According to Reiter, the current cost for Cape Charles is 1.2 cents per gallon, 70% of which is fixed cost. If the county were to pay on this schedule, assuming a flow of 15,000 gallons per day, Cape Charles would net $50,000 in profit over the year. Much to the Countyโs chagrin, Cape Charles wants to charge 1.5 cents per gallon instead. โBut, this difference could be worked out fairly easily,โ said Reiter.
The second issue is over the connection fee. Presently, Cape Charles is insisting that the County pay for connections according to the current schedule (roughly $12,000 for Town Residents). This fee would have to be paid up front, at an estimated cost to the County of $750,000. On day one, the County would have to cut that check to the town. It would also increase the cost of the project from $2.6 million, to $3.3 million.
โWe have also heard that Cape Charles is not interested in any further negotiations until the BoS deals with their zoning request at Rt. 184 and Rt. 13,โ added Reiter. Mr. Reiter is referring to the Townโs desire to create an overlay district at this location.
โBlackmail,โ said Katie Nunez. โWe havenโt received anything in writing to that effect. That is just what was reported from the last Town Council meeting.โ
โIt does make life interesting,โ said Hubbard.
โThe contract says a surcharge of 10 percent, but now they are asking for 26 percent, the 1.5 cents per gallon. What is the surcharge for?โ asked LeMond.
โFor them being good guys and letting us export our product for them to process,โ said Reiter.
Chairman Hubbard questioned where the current estimates of usage were coming from. Nunez noted that engineers have surveyed various properties that might be involved, and extrapolated out from there.
โWe are crystal balling this, absolutely,โ added Reiter. โIf you can tell me whatโs going to be built out there, I can give you a good number.โ
Supervisor Hogg still had questions about usage, and profits to Cape Charles based on the 1.2 cents per gallon costs. โThey already have their budget and they are paying these costs today, without any input from the PSA. When they get our input, that is extra money. They already balanced the budget without us, so the money they get from us is bonus money,โ responded Nunez.
โBut, we have been stagnant for so long. Where did we come up with these numbers?โ asked Hogg.
โWe are doing this based on growth out there,โ said Reiter. โEither you are going to predict that you are going to have growth out there, or we can just close up shop and go home.โ
โI guess the assumption is then, that some will move in from the north, or elsewhere, to take advantage of the sewer system,โ said Hogg.
โNot necessarily. Tourism, or more commercial properties catering to tourism,โ said Reiter.
โThe concept of this project was for more commercial development,โ added Hubbard.
โThat is the directive the PSA received from the board, and that is what this is,โ said Reiter.
โAnd that is what Cape Charles wants to talk about,โ said LeMond.
Another sticky point brought up by Reiter, is the special tax district, and whether or not property owners should be allowed to opt out. According to Reiter, it is the consensus of the PSA that they should be allowed to opt out, but this option does come with some caveats. If the property owner decided later that they wanted to opt in, they would have to pay a special tax (10 year) and a penalty for connecting. This would end up being โa very hefty bill.โ The other drawback is that the cost would then have to be spread out amongst those that opted in, making it more expensive.
A related issue is how much of the cost should be borne by the property owner vs. how much should be paid by the general tax. The PSA currently believes the split should be 50/50, essentially doubling the property ownerโs tax. The original thought was a 75/25 split, but due to the increased cost of project, the PSA feels a 50/50 is more reasonable.
โIsnโt it true, that if they opt in, their property values will go up?โ asked LeMond.
โThat is up to the Commissioner of Revenue,โ said Nunez. โThis will not be borne out until we see sales activities go up. Most valuations are set by sales activity.โ
PSA member, Taylor Dukes of Exmore added, โIn Exmore, it was thought, if they build it they will come. We did not see it, most of the traffic is still north, mainly in Accomack. I hate to see the County go into debt, and the building not come. In Exmore, it did not come.โ
Moving forward, Reiter said the Board needed to pay the upfront startup costs, as well as back the Bonds that will be issued by the PSA. Bob Panek added that, to clarify the Cape Charles position, the fees are to be used to pay for plant expansion, once the additional usage pushes it to capacity.
After the PSA adjourned to the adjoining conference room, the Board continued the debate. โAm I to understand that the PSA is on hold until the Board deals with these issues?โ asked Nunez.
โUntil we hear from Cape Charles, this is all we can do,โ said Hubbard.
โI just want to understand what on hold means,โ said Nunez. โDoes it mean no set work, or that the PSA does not need to meet any longerโno nothing?โ
โThere are some things we have to do. Until then, there is nothing they can do,โ said LeMond.
โThat is what Iโm asking. Should the Board still be working on this? Should I put it on the agendaโor not,โ asked Nunez.
โWe are waiting on Cape Charles,โ said Hubbard. โI donโt see spending any more money until we know whatโs going on. We should not move forward until we have more support from the citizenry.โ
โSo, youโre killing the project. Just so weโre all clear,โ said Nunez.
โPutting a hold on the project,โ said LeMond.
โSo, Iโm not supposed to do any work on this? Iโm trying to understand,โ said Nunez.
โThere are steps,โ said LeMond. โUntil we can proceed.โ
โSo, you are not going to pursue those steps. Or are you?โ asked Nunez. “Iโm trying to understand you.โ
Board voted 3-1 to put the PSA project on hold, with Trala opposed.

It’s about time. Both the citizens and the majority of the property owners in the southern node “special tax district” have made it abundantly clear they don’t want this project. It is time to kill the PSA for good.